Published on Monday, 1 May 2023 at 4:00:00 PM
Several significant Shire works projects located on Bindi Bindi-Toodyay Road have recently been completed by our construction team, making it a smoother and safer road for Toodyay travellers.
Federal Black Spot Program Reconstruction
Three kilometres of Bindi Bindi-Toodyay Road (SLK 0.00-3.00) have been reconstructed as part of the Federal Black Spot Program.
This program offers funding for nominated road locations where vehicle accidents are a high risk, allowing changes and improvements to be made that reduce that risk. The Shire of Toodyay’s funding has allowed us to complete:
- 33,000m² of road formation;
- 28,000m² of sealed road (including primer and a two-coat seal);
- 800m of W-BEAM barrier;
- 320m of mountable concrete kerbing;
- 9000m of line marking; and
- 300 raised pavement markers, guideposts, and culvert markers.
Sealing and Asphalt Intersection Upgrade
We have also completed sealing works and an asphalt intersection on another two-kilometre section of Bindi Bindi-Toodyay Road (SLK 14.20-16.20).
These upgrade works resulted in 17,000m² being mixed, trimmed, and compacted - with line marking to be conducted within the next few weeks.
A big shoutout goes to our hardworking construction team for their achievements in reaching both of these project milestones, and for making our Shire a safer place to be behind the wheel – keep up the fantastic work.